Client
Indemitsu Boggabri Coal Pty Ltd.
Project Manager
Stephen Wood, Directing Manager
Project Value
Approx. $1.5 million
Duration
10 weeks on site, 6 weeks design
Project Description
Civilbuild had just completed one of its most challenging projects – to build a three span, heavy duty concrete bridge over the Kamilaroi Highway near Boggabri in 10 weeks. The bridge had to carry over loaded B double’s hauling coal on a private road to the nearby rail head. The bridge was 42.4m long and 10m wide.